Annex
3
Terms
of Reference for Individual External Review Team Members.
Team
Members
Dr.
Stephan Bass, Director, International
Institute for Environment and Development
Dr.
Aziz Bouzaher, Senior Environment/Natural Resource Economist and Team
Leader, Pakistan/Afghanistan, Nepal, and Bhutan Environment, the World
Bank, Washington, D.C., USA.
Dr.
Arthur J. Hanson (Team Leader), Distinguished
Fellow and Senior Scientist, International
Institute for Sustainable Development (IISD)
Dr.
G.M. Samdani, Senior
Environmental Management Consultant, Pakistan
Terms
of Reference Dr. Arthur J. Hanson (Team Leader)
November
1999 March 2000
General
The
partners in Pakistan Environment Programme have prepared a TOR for the
MTR of the Pakistan National Conservation Strategy and initiated a number
of activities. The MTR is intended to provide stakeholders (government,
civil society and supporting institutions) with the opportunity to assess
the current situation and set the stage for any necessary mid-term corrections.
Specifically the MTR will assess progress since the 1992 adoption of the
NCS and, based on lessons learned, will draw conclusions and make recommendations
on adjustments needed for the NCS and integrated strategic guidelines
for sustainable development in Pakistan. The External Review Team, comprised
of four members, will prepare a draft final report of the MTR and present
it to a multisectoral workshop. Based on comments received at the workshop,
a final report of the MTR will be submitted to the Ministry of Environment
for wider circulation to stakeholders and further action.
The
ERT will conduct its work from a combination of materials prepared in
advance by the NCS MTR Team, from interviews and field visits in various
areas of Pakistan, from review of documents of the NCS and other development
efforts in Pakistan, through limited comparisons with best-practice
strategies in other countries, and from the individual experience of the
ERT members. Background work and responses regarding the design and preliminary
products arising from the advance work commissioned through IUCN-Pakistan
will take place in the months prior to the ERT meetings. Team activities
within Pakistan are scheduled for a three-week period during March - April
2000. It is anticipated that the final report will be produced by mid
of April 2000.
The
ERT members will work cooperatively to produce an integrated report. However,
it is useful to draw upon the individual skills and background of each
person in the conduct of the fieldwork and other activities. These individual
TOR are provided as Annex 2 to the overall TOR for the ETR, which, in
turn, are linked to the TOR for the MTR. These documents should be consulted
for further details regarding the tasks.
Specific
-
The Team Leader
is responsible for submitting a satisfactory draft and final report
for the MTR and for maintaining liaison with key members of the team
responsible for organizing and conducting the MTR.
-
In the period
leading up to the field visit, review and comment upon materials received
from the MTR Coordinator and Head of IUCN Islamabad related to the
following aspects of the MTR: design of an analytical framework; focus
group reporting; review of institutions, provincial and district strategies,
legislation, mass awareness, resourcing the NCS and progress and impact
of a sample of NCS projects; and other items that may be of concern.
-
Prior to the field
visit, review relevant background materials on the NCS and reports
submitted as part of the MTR.
-
Establish and
maintain contact with other ERT members and help to prepare acceptable
TOR for their activities under the MTR.
-
In cooperation
with the MTR Coordinator and Head of IUCN Islamabad Office work out
a detailed agenda for field visits and other activities within Pakistan
related to the ERT visit.
-
Establish, in
cooperation with other ERT members in advance of the field visit,
the basis for international best-practice comparisons
to be used in the NCS MTR.
-
Take the lead
in those aspects of the work related to overall strategies of sustainable
development, and in the preparation of sections of the report related
to general aspects of this theme.
-
Conduct interviews,
participate in meetings, including the 2-day multisectoral workshop,
and undertake visits to various parts of Pakistan as may be deemed
appropriate during the course of the field visit.
-
Carry out the
work described above in a fashion that will provide concise and practical
recommendations for the future of the NCS and its management, responding
to points 1-7 raised in the ERT TOR.
Terms
of Reference Dr. Stephan Bass (Team Member)
November
1999 March 2000
General
The
partners in Pakistan Environment Programme have prepared a TOR for the
MTR of the Pakistan National Conservation Strategy and initiated a number
of activities. The MTR is intended to provide stakeholders (government,
civil society and supporting institutions) with the opportunity to assess
the current situation and set the stage for any necessary mid-term corrections.
Specifically the MTR will assess progress since the 1992 adoption of the
NCS and, based on lessons learned, will draw conclusions and make recommendations
on adjustments needed for the NCS and integrated strategic guidelines
for sustainable development in Pakistan. The External Review Team, comprised
of four members, will prepare a draft final report of the MTR and present
it to a multisectoral workshop. Based on comments received at the workshop,
a final report of the MTR will be submitted to the Ministry of Environment
for wider circulation to stakeholders and further action.
The
ERT will conduct its work from a combination of materials prepared in
advance by the NCS MTR Team, from interviews and field visits in various
areas of Pakistan, from review of documents of the NCS and other development
efforts in Pakistan, through limited comparisons with best-practice
strategies in other countries, and from the individual experience of the
ERT members. Background work and responses regarding the design and preliminary
products arising from the advance work commissioned through IUCN-Pakistan
will take place in the months prior to the ERT meetings. Team activities
within Pakistan are scheduled for a three-week period during March - April
2000. It is anticipated that the final report will be produced by mid
of April 2000.
The
ERT members will work cooperatively to produce an integrated report. However,
it is useful to draw upon the individual skills and background of each
person in the conduct of the fieldwork and other activities. These individual
TOR are provided as Annex 2 to the overall TOR for the ETR, which, in
turn, are linked to the TOR for the MTR. These documents should be consulted
for further details regarding the tasks.
Specific
-
This Team Member
is responsible for assisting in the preparation of a satisfactory
draft and final report for the MTR, with a lead role in the preparation
of one or more sections, based upon agreement among the various team
members.
-
In the period
leading up to the field visit, review and comment upon materials received
from the MTR Coordinator and Head of IUCN Islamabad related to the
following aspects of the MTR: design of an analytical framework; focus
group reporting; review of institutions, provincial and district strategies,
legislation, mass awareness, resourcing the NCS and progress and impact
of a sample of NCS projects; and other items that may be of concern.
-
Prior to the field
visit, review relevant background materials on the NCS and reports
submitted as part of the MTR.
-
Respond to the
Team Leader upon request regarding issues of design, organization,
logistics, scheduling, information needs or other matters.
-
Establish, in
cooperation with other ERT members in advance of the field visit,
the basis for international best-practice comparisons
to be used in the NCS MTR and take a lead in suggestions related to
natural resource and ecological themes.
-
Take the lead
in those aspects of the work related to natural resource topics, biodiversity
and in the preparation of sections of the report related to general
aspects of these themes. Also to explore the nexus between an NCS
and NSSDs.
-
Conduct interviews,
participate in meetings, including the 2-day multisectoral workshop,
and undertake visits to various parts of Pakistan as may be deemed
appropriate during the course of the field visit.
-
Carry out the
work described above in a fashion that will provide concise and practical
recommendations for the future of the NCS and its management, responding
to points 1-7 raised in the ERT TOR.
Terms
of Reference Dr. Aziz Bouzaher (Team Member)
November
1999 March 2000
General
The
partners in Pakistan Environment Programme have prepared a TOR for the
MTR of the Pakistan National Conservation Strategy and initiated a number
of activities. The MTR is intended to provide stakeholders (government,
civil society and supporting institutions) with the opportunity to assess
the current situation and set the stage for any necessary mid-term corrections.
Specifically the MTR will assess progress since the 1992 adoption of the
NCS and, based on lessons learned, will draw conclusions and make recommendations
on adjustments needed for the NCS and integrated strategic guidelines
for sustainable development in Pakistan. The External Review Team, comprised
of four members, will prepare a draft final report of the MTR and present
it to a multisectoral workshop. Based on comments received at the workshop,
a final report of the MTR will be submitted to the Ministry of Environment
for wider circulation to stakeholders and further action.
The
ERT will conduct its work from a combination of materials prepared in
advance by the NCS MTR Team , from interviews and field visits in various
areas of Pakistan, from review of documents of the NCS and other development
efforts in Pakistan, through limited comparisons with best-practice
strategies in other countries, and from the individual experience of the
ERT members. Background work and responses regarding the design and preliminary
products arising from the advance work commissioned through IUCN-Pakistan
will take place in the months prior to the ERT meetings. Team activities
within Pakistan are scheduled for a three-week period during March - April
2000. It is anticipated that the final report will be produced by mid
of April 2000.
The
ERT members will work cooperatively to produce an integrated report. However,
it is useful to draw upon the individual skills and background of each
person in the conduct of the fieldwork and other activities. These individual
TOR are provided as Annex 2 to the overall TOR for the ETR, which, in
turn, are linked to the TOR for the MTR. These documents should be consulted
for further details regarding the tasks.
Specific
-
This Team Member
is responsible for assisting in the preparation of a satisfactory
draft and final report for the MTR, with a lead role in the preparation
of one or more sections, based upon agreement among the various team
members.
-
In the period
leading up to the field visit, review and comment upon materials received
from the MTR Coordinator and Head of IUCN Islamabad related to the
following aspects of the MTR: design of an analytical framework; focus
group reporting; review of institutions, provincial and district strategies,
legislation, mass awareness, resourcing the NCS and progress and impact
of a sample of NCS projects; and other items that may be of concern.
-
Prior to the field
visit, review relevant background materials on the NCS and reports
submitted as part of the MTR.
-
Respond to the
Team Leader upon request regarding issues of design, organization,
logistics, scheduling, information needs or other matters.
-
Establish, in
cooperation with other ERT members in advance of the field visit,
the basis for international best-practice comparisons
to be used in the NCS MTR and take a lead in suggestions related to
pollution control, energy, urban issues, environmental assessment,
institutional development and capacity building.
-
Take the lead
in those aspects of the work noted under item 5 above and also on
issues of foreign donor support and technical assistance, with special
emphasis on Banks perspective, and in the preparation of sections
of the report related to general aspects of these themes.
-
Conduct interviews,
participate in meetings, including the 2-day multisectoral workshop,
and undertake visits to various parts of Pakistan as may be deemed
appropriate during the course of the field visit.
-
Carry out the
work described above in a fashion that will provide concise and practical
recommendations for the future of the NCS and its management, responding
to points 1-7 raised in the ERT TOR.
Terms
of Reference Dr. G.M. Samdani (Team Member)
November
1999 March 2000
General
The
partners in Pakistan Environment Programme have prepared a TOR for the
MTR of the Pakistan National Conservation Strategy and initiated a number
of activities. The MTR is intended to provide stakeholders (government,
civil society and supporting institutions) with the opportunity to assess
the current situation and set the stage for any necessary mid-term corrections.
Specifically the MTR will assess progress since the 1992 adoption of the
NCS and, based on lessons learned, will draw conclusions and make recommendations
on adjustments needed for the NCS and integrated strategic guidelines
for sustainable development in Pakistan. The External Review Team, comprised
of four members, will prepare a draft final report of the MTR and present
it to a multisectoral workshop. Based on comments received at the workshop,
a final report of the MTR will be submitted to the Ministry of Environment
for wider circulation to stakeholders and further action.
The
ERT will conduct its work from a combination of materials prepared in
advance by the NCS MTR Team , from interviews and field visits in various
areas of Pakistan, from review of documents of the NCS and other development
efforts in Pakistan, through limited comparisons with best-practice
strategies in other countries, and from the individual experience of the
ERT members. Background work and responses regarding the design and preliminary
products arising from the advance work commissioned through IUCN-Pakistan
will take place in the months prior to the ERT meetings. Team activities
within Pakistan are scheduled for a three-week period during March - April
2000. It is anticipated that the final report will be produced by mid
of April 2000.
The
ERT members will work cooperatively to produce an integrated report. However,
it is useful to draw upon the individual skills and background of each
person in the conduct of the fieldwork and other activities. These individual
TOR are provided as Annex 2 to the overall TOR for the ETR, which, in
turn, are linked to the TOR for the MTR. These documents should be consulted
for further details regarding the tasks.
Specific
-
This Team Member
is responsible for assisting in the preparation of a satisfactory
draft and final report for the MTR, with a lead role in the preparation
of one or more sections, based upon agreement among the various team
members.
-
In the period
leading up to the field visit, review and comment upon materials received
from the MTR Coordinator and Head of IUCN Islamabad related to the
following aspects of the MTR: design of an analytical framework; focus
group reporting; review of institutions, provincial and district strategies,
legislation, mass awareness, resourcing the NCS and progress and impact
of a sample of NCS projects; and other items that may be of concern.
-
Prior to the field
visit, review relevant background materials on the NCS and reports
submitted as part of the MTR.
-
Respond to the
Team Leader upon request regarding issues of design, organization,
logistics, scheduling, information needs or other matters.
-
Establish, in
cooperation with other ERT members in advance of the field visit,
the basis for international best-practice comparisons
to be used in the NCS MTR and take a lead in suggestions related to
the applicability of such comparisons to Pakistan, in the context
of its development efforts.
-
Take the lead
in those aspects of the work related to the social aspects of development,
including matters related to population and cultural aspects, and
to the economy in Pakistan, keeping in view the functioning of public
sector and other related issues, and in the preparation of sections
of the report related to general aspects of these themes.
-
Conduct interviews,
participate in meetings, including the 2-day multisectoral workshop,
and undertake visits to various parts of Pakistan as may be deemed
appropriate during the course of the field visit.
-
Carry out the
work described above in a fashion that will provide concise and practical
recommendations for the future of the NCS and its management, responding
to points 1-7 raised in the ERT TOR.
|